Application of Grouted Mechanical Couplers in Accelerated Bridge Construction

Open Access

Year : 2023 | Volume :8 | Issue : 1 | Page : 32-48
By

Yoon-Si Lee

Travis Hosteng

  1. Associate Professor Bradley University Peoria, Illinois USA
  2. Assistant Professor Iowa State University Ames, Iowa USA

Abstract

This paper presents two research projects that investigated the performance of the grouted coupler connection details developed for Accelerated Bridge Construction applications. The goal of the first project was to conduct laboratory test and evaluation of the grouted rebar coupler connections similar to those utilized on the Keg Creek Bridge on U.S. Highway 6, the first replacement bridge in Iowa constructed entirely with modular and Accelerated Bridge Construction technologies. The connections of focus were between the pier column and the pier cap, and between the pier column and the drilled shaft. Laboratory Specimens were fabricated such that they were representative of the pier column connections of the Keg Creek Bridge, and tested for their strength and durability, mainly resistance to crack initiation and propagation at the joints. The success of the first project led to a follow-up study that investigated the performance of three novel integral abutment connection details that were designed for mechanically splicing the integral diaphragm and cap beam. The test results showed that the grouted coupler connection details, if properly incorporated, would provide bridge owners and engineers with viable options for improving the constructability and durability of their bridges.

Keywords: Accelerated bridge construction; connections; pier columns; integral abutment.

[This article belongs to International Journal of Construction Engineering and Planning(ijcep)]

How to cite this article: Yoon-Si Lee, Travis Hosteng. Application of Grouted Mechanical Couplers in Accelerated Bridge Construction. International Journal of Construction Engineering and Planning. 2023; 8(1):32-48.
How to cite this URL: Yoon-Si Lee, Travis Hosteng. Application of Grouted Mechanical Couplers in Accelerated Bridge Construction. International Journal of Construction Engineering and Planning. 2023; 8(1):32-48. Available from: https://journals.stmjournals.com/ijcep/article=2023/view=90548

Full Text PDF Download

Browse Figures

References

1. ASCE 2021. Infrastructure report card. Available from: https://infrastructurereportcard.org/cat-item/bridges. American Society of Civil Engineers (ASCE); 2021.
2. Lee YS, Soltani M, Schweigert K, Maharjan S. Prevention and repair of end-region cracks in prestressed concrete girders: A state-of-the-art review. Int J Civ Struct Eng Research. 2019;7(1):134–45. doi: 10.5281/zenodo.6014921.
3. Lee Y, Wipf TJ, Phares BM, Klaiber FW. Evaluation of Steel Girder Bridge Strengthened with Carbon Fiber–Reinforced Polymer Posttension Bars. Transportation Research Record. 2005;1928(1):232–44. doi: 10.1177/0361198105192800125.
4. ARTBA. Bridge condition report. Available from: https://artbabridgereport.org/reports/2021-ARTBA-Bridge-Report.pdf. Vol. 2021. American Road & Transportation Builders Association (ARTBA); 2021.
5. H.R. 3864–117th Congress; 2021–2022. Infrastructure investment and jobs act [cited Nov 15, 2021]. Available from: https://www.congress.gov/bill/117th-congress/house-bill/3684/text.
6. Accelerated Bridge Construction University Transportation Center (ABC-UTC), US Department of Transportation, Office of the Assistant Secretary for Research and Technology. Available from: https://www.transportation.gov/content/university-transportation-centers.
7. Azizinamini A. Accelerated bridge construction. J Bridge Eng. 2020;25(12):02020002. doi: 10.1061/(ASCE)BE.1943–5592.0001643.
8. Schweigert K, Lee YS, Gastel C, Maharjan S. Accelerated bridge construction and its recent trend. Int J Adv Res Sci Eng. 2018;7(8):50–8. doi: 10.5281/zenodo.6015015.
9. Phares BM, Lee YS, Hosteng TK, Nelson J. Investigation of grouted coupler connection details for accelerated bridge construction. Transportation Research Record. 2021;2675(8):562–9. doi: 10.1177/0361198121999393.
10. Jansson PO. Evaluation of grout-filled mechanical splices for precast concrete construction. Report No. R-1512. Available from: https://www.michigan.gov/documents/mdot/MDOT_Research_Report_R1512_234541_7.pdf. Michigan Department of Transportation; May 2008.
11. Littleton P, Mallela J, Iowa Demonstration Project. Accelerated bridge construction on US 6 over keg creek [final report]. Available from: https://rosap.ntl.bts.gov/view/dot/54259. Highways for life. Federal Highway Administration; June 2013.
12. Iowa DOT. U.S. 6 bridge over keg creek: photo. Gallery Press; 2011. Available from: https://iowadot.gov/us6kegcreek/.
13. Rowell SP, Grey CE, Woodson SC, Hager KP. High strain-rate testing of mechanical couplers; ERDC TR-09–8. Vicksburg, MS: United States Army Corps of Engineers, Engineer Research and Development Center; September 2009.
14. Lee M, Wernly M, Garret B, Stanton JF, Eberhard MO, Weinert M Report 698. Application of ABC connections in moderate-to-high seismic regions. Washington, DC: Transportation Research Board; 2011.
15. Restrepo JI, Tobolski MJ, Matsumoto EE Report 681. Development of a precast bent cap system for seismic regions. Washington, DC: Transportation Research Board; 2011.
16. Motaref S, Saiidi M, Sanders DH. Seismic response of precast bridge columns with energy dissipating joints. Report No. CCEER-11–01. Center for Civil Engineering Earthquake Research; 2011. p. 760.
17. Hironobu A. Cyclic loading experiment of precast columns of railway rigid-frame viaduct installed with NMB splice sleeves. Proceedings of the Japan Concrete Institute. Vol. 27(2); 2005.
18. Huang SW, Yu JT, Chiou HD, Asakawa T, Tsai KC. Final report of experiment on precast reinforced concrete beam-column assemblage. Chinese Society of Structural Engineering; 2011.
19. Iowa DOT. Plans of US 6 over keg creek: BRF-006–1(114)-38–78; 2011. 780061114 Plan revision [cited June 2011]. Available from: https://iowadot.gov/us6kegcreek/documents/Revisions78_0061_114.pdf.
20. Hosteng TK, Phares BM, Abu-Hawash A, Bierwagen D, Nelson J. Laboratory investigation of grouted coupler connection details for ABC bridge projects Trans Project 12–441. Ames, IA: Bridge Engineering Center, Iowa State University; 2015.
21. AASHTO LRFD. Bridge design specifications. 6th ed. Washington, DC: American Association of State Highway and Transportation Officials; 2012.
22. Hosteng TK, Phares BM, Strength RS. Durability, and application of grouted couplers for integral abutments in Accelerated Bridge Construction Trans Project 12–441. Ames, IA: Bridge Engineering Center, Iowa State University; 2016.
23. Shafei B, Hosteng TK, DeJong A. Integral abutment connection details for accelerated bridge construction. Ames, IA: Bridge Engineering Center, Iowa State University; 2018.